The building of the State School in Belchertown was a major uplift to the local economy and provided full and part-time employment for many Belchertown residents. The community's economy was sound, and unemployment was unheard of. With State Retirements, many residents enjoyed a secure Old Age. The Campus became a beautiful tree-shaded park with lovely, well maintained buildings, providing services such as Sunday Movies to the entire community. Those working with the Residents frequently developed deep rooted and affectionate, supportive relationships and many fond memories. Life was good for Belchertownians !
The 1970's however saw a series of state wide lawsuits between Residents, Guardians and the Commonwealth over institutionalization of the Residents. In fact the lives of those cloistered away from society, sometimes drugged to control behavior, was less then ideal in this otherwise bucolic environment. Separation from society was deemed inappropriate by the courts, which ordered closure of some 12 major State School facilities, and a number of minor facilities, replaced with construction of many new individual community living units throughout the Commonwealth.
The word closure was received in Belchertown in the late 1970's and folks began to retool. Future use of the facility was open to public suggestion, and a Reuse Committee, the forerunner of today's EDIC, was formed to develop a plan for the facility. There was general agreement that what ever replacement came in, it must be designed to expand the tax base and employment opportunity. In 1992, the Commonwealth offered to reuse and reconstruct the facility as a Minimum Security Prison, and, after much heated discussion (and emotion!), the States offer was declined by residents in a general ballot vote. At the 1992 May Annual Town Meeting, voters, under authorization of MGL Chapter 121 of the General Laws of the Commonwealth, authorized the formation of a Belchertown Economic Development and Industrial Corporation to undertake development of a reuse plan for the State School campus.
The 1990's saw a lot of studies, mostly resulting in reuse of the State School as some form of residential living facility, possibly with businesses incorporated, mostly designed for support of an aging population. However, any residential use in an otherwise fast growing community did not sit well. Increased Tax Base with jobs was the towns priority. Little happened until the beginning of the 2000's, when the EDIC Directors negotiated a Purchase and Sale Agreement with the Commonwealth and became the owners of record of some 300 acres of land with buildings (The remaining adjoining acreage went to the Commonwealth's Department of Agriculture and was leased for 15 years to the New England Small Farm Institute).
The Town, in need of land for schools, recreation and municipal services, acquired three parcels of land from the Commonwealth in the 1980's and 1990's. Two of these parcels now contain a new Middle School, Elementary School, indoor pool, and organized recreation playing fields. The third parcel was obtained by the town with five buildings and is now in use for three renovated elementary school buildings, a Recreation Department Office and Teen Center, Public Access Cable TV Center, American Legion facility, and, with the addition of two newly constructed buildings, a Senior Center and Police Station.
A newly authorized Business and Technology Park overlay zone was deemed to be most supportive of smaller business operations, and held incentives that were designed to encourage business development with the least amount of bureaucratic hassles, by gaining pre-approvals from key town boards. The Planning Board approved the BEDIC's request, and all State School land zoned General Business and Light Industry came under the Business and Technology Park overlay zone.
The BEDIC also gained state approval in 2002 to become a part of the existing Quabbin Valley Economic Target Area. Subsequently, the State School parcels were approved and designated by Town Meeting to be an Economic Opportunity Area, a designation authorized under Mass General Law, Chapter 40, sec 59. Developers of State School property, under this law, make take advantage of the opportunity to negotiate with town officials, and secure Town Meeting approval for desirable tax incentives.
New businesses can receive State Tax Incentives, including 5% Investment Tax Credit and 10 % Tax Credit for refurbishing a two-year or more abandoned building. The Developer can negotiate a Tax Incentive Finance agreement with the town, applying for Municipal property tax incentives such as Special Tax Assessments (A phased in assessment of the total value of the property) OR Tax Increment Financing Agreement (bleeding in the new tax base to 100% over 5-20 years). Finally, Federal 20% Historic Tax Credits may also be available for refurbishing existing historic buildings.
The BEDIC's land came in three distinct parcels, referred to as Parcels B, D & E. Parcels D & E contained no buildings. Parcel E, containing 43 acres, was sold to a Developer for the Cold Spring Business Park now under development. Parcel D, containing 52 acres (including 20 wet land acres) is under agreement with the Pioneer Valley Transit Authority for development of a regional Intra-model Transportation Center and the future Eastern Hampshire County District Court House. The possibility exists for other State service centers to follow along with facilities for expanded services in support of the Court. Parcel B contained a combination of open land, some 30 existing structures, 22 acres of Agriculturally Zoned land and some 30 acres of wet land being designed now as a public park.
The BEDIC began active efforts to develop Parcel B in a manner designated by the Town Meeting mandate. Through the towns Council on Aging, and the efforts of its Committee on Assisted Living, a developer was identified to bring into being a 60 unit Assisted Living Facility, re-developing the former Infirmary and Hospital Buildings, along with 60 new Age Restricted Condos. A Nursing Home provider is now being sought, to be a part of an Aging in Place continuum.
Three phases of development for Parcel B are anticipated. Phase One, now in the development stage, would have two entrance roads totaling 1800 feet, with lots containing vacant land or land with buildings. Tighe & Bond Engineering, Inc. was retained to prepare detailed engineering design plans, which were presented to, and approved by, the Belchertown Planning Board in 2003. These plans, now recorded in the Registry of Deeds, enable the BEDIC to begin selling parcels to interested businesses in 2004. Phase Two, will connect the two entrance roads into a 3000 foot long, 28 foot wide improved road, creating a modified Town Center By-pass from State Route 202, north to Jackson Street, and, with town effort, eventually connecting with Route 9 to Amherst. Phase Three will create a westerly loop road of some 1500 feet, and will be developed as required.
Eight inch water lines will connect to the Town's new and expanded pumping and storage facilities, and will replace existing ageing lines through Phases I & II, with connections to the town's system at both ends. Similarly new twelve inch gravity sewer lines will connect, in Phase I & II, to existing town sewer lines at both ends, leading to the Town's new $10 million state-of-the-art treatment facility.
Designed storm drains and related control facilities will be installed to engineered plans and town approved standards for some 3000 road feet, containing storm runoff on-site.
Remaining infrastructure, including three phase underground electric service, designed by Mass Electric, telephone cable, and fiber optic communication cable will service all segments of Phase I & II
While lots, containing open land or land with existing buildings, have been identified on drawings, actual lot surveys await the desires of purchasers. Lots tend to be seen in 1 to 3 acre parcels, but can be designed for larger parcels, such as the Assisted Living Facility, as needed.
Insuring compatibility in use, and transition between the varying envisioned segments is important in planed land use, and will guide the BEDIC Directors in placing businesses. The former State School design and layout supports this use process, and is largely being followed for the property's next life.
Local Boards have reviewed these plans and have been most supportive. Tighe Bond Engineering, an established and experienced firm, brings in the technical skills required in insuring quality structural design and infrastructure support.
Ambiance is important, and architectural design standards, developed by the Corporation, should not only insure compliance with citizen expectations, but provide a healthy, supportive and desirable business environment for new and growing businesses, in a rapidly growing residential community, while ultimately meeting the designated goals of providing jobs and expanding the tax base in a community compatible, and business desirable setting.
The 'children' at the school range in age from one year old to 88 years old. Although many are grown men and women, their minds never developed beyond childhood. The older 'children' are capable of a great deal, however, and with adult supervision, carry on most of the work done at the school. Many do beautiful handcraft work and win prizes at the local fair. Many of the younger 'children' attend regular school classes on the grounds and are able to graduate from the sixth grade.
The school has provided steady employment for the townspeople even during difficult years. In emergencies, the town uses the school's water system and now uses its filter beds. During World War II the State School's telephone office served as an air raid warning station, and now serves as the regional communications center for the Civil Defense organization. In all, Belchertown and its State School are an excellent example of community cooperation.